What changed: After the November 11 inspection, it became known that the third section of Phaniad Chang Road had been completed; repairs on the fourth section continue. The mayor ordered faster asphalt paving of the main road ahead of the fireworks festival on November 27–28, while the report still gives a contract deadline in January 2027.
Repairs on Soi Paniad Chang / Phaniad Chang Road in Pattaya continue. According to “Pattaya News,” after Mayor Poramet Ngampichet’s inspection on November 11, one section has already been completed, while work was still underway on another. The mayor demanded faster asphalt paving of the main road before the International Fireworks Festival, scheduled for November 27–28, 2026.
An instruction to finish paving by the festival does not mean that the entire street is already open. The reports still give a contract deadline in January 2027, and whether you can drive up to a specific address depends on conditions on the ground. This matters both for residents of the area and for people arriving by taxi. General transport options are collected in the article about transport in Pattaya. Current as of publication.
What is known
According to “Pattaya News,” the mayor inspected the road work on November 11 at 16:00. The outlet reported the completion of the third section from the Tantraruk / Tantarak Intersection to Sukhumvit-Pattaya 32 Road. On another stretch, near the Khon La Fan restaurant, work was still underway.
According to the October report from the same outlet, the project covers about 3,477 m of road with a carriageway width of 6–8 m. The plan calls for laying asphalt concrete over the existing concrete and replacing the covers of the drainage wells. At the kickoff meeting, neither the contractor nor the contract cost was named.
Completion of one section does not confirm the handover of the entire road. The report on the inspection describes the progress of the work and the authorities’ expectations, but it does not report the actual acceptance of the entire project.
Road repairs in Pattaya: which Phaniad Chang sections are ready
In October, “Pattaya News” published a breakdown of the work into four sections:
- Soi Lukdod near Big C Extra, between North Pattaya Road and Central Pattaya Road. No separate up-to-date status is given.
- From Sukhumvit Road to the Tantarak Intersection. The November report does not confirm that this section has been completed.
- From the Tantarak Intersection to Sukhumvit-Pattaya 32. Completed, according to the November report.
- From the Khon La Fan restaurant to the Mum Aroi Intersection, toward Pattaya Third Road. Work was still underway during the November 11 inspection.
The mayor expected improvements on the four routes to be finished soon, but that was a forecast, not a report of their acceptance. The November report separately describes the main Phaniad Chang Road as a route more than two kilometers long; this does not contradict the October overall length of the work, 3,477 m.
When the work will be finished: the contract and the fireworks festival
According to the October report from “Pattaya News,” the contract period for the work — from October 1, 2026 to January 18, 2027. In the November report, the outlet gives January 17–18, 2027. Without the contract itself, the single exact legal end date cannot be confirmed.
After the inspection, the mayor demanded faster work and completion of the asphalt paving before the International Fireworks Festival. The event is scheduled for November 27–28, 2026 at Pattaya Beach: the dates are confirmed in the official events calendar of the Tourism Authority of Thailand and in the events calendar on the Thai government portal.
However, the festival calendar does not confirm that the road is ready. According to the plan, the asphalt must be laid first, and only then are the manhole covers leveled with the new surface. Therefore, the appearance of fresh asphalt does not yet mean that all work is finished.
What is changing in the surface and on the sidewalks
Repairs on Phaniad Chang Road involve an asphalt-concrete surface laid over the existing concrete base. According to the November “Pattaya News” report, the asphalt is laid in two layers with a total thickness of about seven centimeters. A separate part of the project is replacing and leveling the covers of the drainage wells.
The outlet also reports on the ramps that have been built, smoother pedestrian surfaces, and accessibility markings for people with disabilities. The city is so far only considering protective barriers in places without nearby homes or dedicated parking. There is no confirmation that such barriers have already been installed.
What to do
If you are heading to Phaniad Chang, follow the temporary signs and the actual traffic arrangements, not only the news that a single section has been completed. Before traveling to a residence, shop, or other address, check with your host or transport provider whether you can reach the exact spot directly.
The authorities did not present a detour map at the October meeting, but this does not mean that there is currently no up-to-date traffic plan. The November report does not provide confirmed details on specific closures, working hours, or detour routes. If you are planning a trip by car or with a driver, you may find helpful the articles about choosing a taxi in Thailand and about road safety in Thailand.
The main difference is simple: speeding up asphalt paving for the festival is the mayor’s instruction, not confirmation that the entire road project is finished. It is best to check whether you can reach specific addresses before setting out.
Sources
- “Pattaya News”: mayor’s inspection, readiness of sections, and instruction to speed up repairs.
- “Pattaya News”: initial project parameters, sections, and contract deadline.
- Tourism Authority of Thailand: November events calendar.
- Thai government portal: dates and venue of the fireworks festival.
Prepared by MyThai.online editorial team.